PCS7系统在2 ×300MW机组湿法烟气脱硫中的应用 App lica tio n o f PCS7 Sys tem in The W e t FGD o f 2 ×300MW Pow e r Un it 陈 程 孙自强 (华东理工大学自动化研究所,上海 200237) 摘 要: 根据石灰石/石膏湿法烟气脱硫的工艺需求,采用西门子的PCS7过程控制系统作为开发平台,设计了一套电厂2 ×300MW机组湿法烟气脱硫控制系统。具体介绍了该控制系统中的硬件配置、网络配置及软件编制等。系统基于Profibus现场总线,采用了多种冗余措施。实践证明,该系统运行稳定可靠,基本实现了石灰石/石膏湿法烟气脱硫过程中多变量连续控制的要求。 关键词: 控制系统 冗余控制 多变量 中图分类号: TQ9 文献标识码: B Abstract: According to the technical requirements of lime stone /gyp sum wet FGD, a control system forwet FGD of 2 ×300MW power units is de2 signed by adopting Siemens′PCS7 p rocess control system as develop ing platform. Hardware configuration, network configuration and software p ro2 gramming of this control system are introduced in detail. The system based on Profibus and several redundantmeasures are included. The practice shows that the system is stable and reliable, and the requirement of the multip le variables continuous p rocess control in the wet FGD is fulfilled. Keywords: Control system Redundant control Multip le variables 0 引言 火电厂减排二氧化硫的主要途径有:煤炭洗选、洁净煤燃烧技术、燃用低硫煤和烟气脱硫,其中烟气脱硫是目前国际上广泛采用控制二氧化硫排放的成熟技术。我国制定的火电厂烟气脱硫技术路线是重点发展石灰石- 石膏湿法脱硫工艺。该工艺是湿法烟气脱硫技术中最主要的技术,尤其适合大机组烟气脱硫,在美国、德国和日本,应用该技术的机组容量约占电站脱硫装机总容量的80%以上,是当前国际上通行的大机组火电厂烟气脱硫的基本工艺,具有脱硫效率高(高达95%以上) 、技术成熟、设备运行可靠性高等特点。 PCS7是一种基于现场总线的模块化新一代过程控制系统,将传统的DCS和PLC控制系统的优点相结合,系统所有的硬件都基于统一的硬件平台,可以根据需要选用不同的功能组件进行系统组态。所有的软件也都全部集成在SIMATIC程序管理器下,有统一的软件平台。系统采用大量新技术,在网络配置上采用标准工业以太网和Profibus网络,消除了DCS和PLC系统间的界限,真正实现了仪控和电控的一体化,充分体现了全集成自动化的特点,使系统应用范围变广,是一种面向所有过程控制应用场合的开放型过程控制系统。 1 工艺流程 石灰石/石膏湿法脱硫工艺系统主要有: 烟气系统、吸收氧化系统、浆液制备系统、石膏脱水系统、排放系统和事故浆液池组成。其中,吸收塔是系统中最重要的设备,其作用是,作为烟道的一部分提供烟气通道;作为吸收容器,所有的吸收反应均在吸收塔内完成。吸收塔自下而上可分为三个区:吸收塔浆液池、洗涤区、气体区,如图1 所示。其基本工艺流程如下:锅炉烟气经电除尘器除尘后,通过增压风机、GGH降温后进入吸收塔。在吸收塔内烟气向上流动且被向下流动的循环浆液以逆流方式洗涤。循环浆液则通过喷浆层内设置的喷嘴喷射到吸收塔中,以便脱除SO2、SO3、HCl和HF,与此同时在“强制氧化工艺”的处理下反应的副产物被导入的空气氧化为石膏(CaSO4 ·2H2O) ,并消耗作为吸收剂的石灰石。循环浆液通过浆液循环泵向上输送到喷淋层中,通过喷嘴进行雾化,可使气体和液体得以充分接触。每个泵通常与其各自的喷淋层相连接,即通常采用单元制。 图1 吸收塔内部结构图 Fig11 Internal structure of absorp tion tower 在吸收塔中,石灰石与二氧化硫反应生成石膏,这